|
In Situ Bioremediation of
Hydrocarbon Contaminated Soils
at
Pepsico FritoLay Simba Isando
Prepared
by G King,
BluePlanet Consulting : August 2010
Introduction
Use of
the vehicle workshop area at the Frito-Lay Simba Isando Plant has
been discontinued due to outsourcing of the distribution chain. An
area in front of the wash bay bounded by the workshops and boundary
walls has been heavily contaminated by hydrocarbon pollutants. These
pollutants were a mixed ranging of Petroleum and Diesel Organics (PRO
and DRO). The total area contaminated covered approximately 300
square metres. The contamination occurred in three main areas, these
being DRO in approximately 30 square metres under the removed diesel
tank, a mix of DRO and PRO in approximately 120 square metres in
front of the wash bay and an area of approximately 90 square metres
of tarmacadam covered soil. The wash bay area was contaminated with a
mixture of petroleum, diesel, oils, alkenes and kerosene. During
initial sampling the average depth of contamination was found to be
150mm below the surface, and therefore a target depth for remediation
was set at 250mm below the surface. In order to re-use this ground
the Company needed to bioremediate the soil to a value below a Total
Petroleum Hydrocarbon (TPH) value of 2000 mg/kg. This value was
chosen based on the fact that the site was industrial and would not
readily be used for agriculture or human occupation in the
foreseeable future. Another factor affecting this target was that the
Department of Water Affairs and Forestry (DWAF) had in the past
recommended the use of a similar target for hydrocarbons at another
industrial site (Snyman 1996).
The area was
enclosed by concrete walls on three sides, with a brick workshop on
the remaining side, creating a situation where In-Situ Bioremediation
was the preferred method due to the following benefits:
No need from
expensive removal of the contaminated soil for off-site clearing.
No need for
a suitable dumping site for the concomitant soil expenses.
No expensive
civil work to remove and replace the walls required.
No need for
extensive replacement of soil and general site reconstruction.
Method
Due to Local
EPA environmental audits, Company was looking speedy resolution to
the contaminated soil problem. On an experimental basis, bioremediate
was selected as the treatment protocol with a target of 12 weeks.
While this is a short time span, but was considered appropriate for
evaluation. In order to facilitate and create favorable conditions
for the successful bioremediation of hydrocarbons in the soil, a
number of factors needed to be considered:
1. Bioremediation of hydrocarbons is a proven treatment protocol of
BluePlanet LLC in the USA. Their products were selected, and their
Technical Staff reviewed the project and recommended a treatment plan
using AquaClean-ACF-32 and AquaClean-HYDRO. These products were
chosen due to the proven effectiveness of the bacterial consortium
contained in the products and the exceptional technical backup
available from BluePlanet LLC as well as from the manufacturer,
Ecological Laboratories, based in Florida USA.
2. The soil needed to be regularly tilled to the depth of the
contamination in order to aerate the soil, providing the most
suitable conditions for the growth of the bacterial colonies.
3. The Carbon:Nitrogen:Phosphate (C 100/N 5/P 1) ratio of the soil
needed to be tested and, if required, corrected to provide the most
suitable nutrient conditions for the growth of the bacterial
colonies.
4. The soil needed to be kept slightly damp, but not wet (saturated),
at all times to provide the most suitable environment for bacterial
growth. Due to the limited time and budget available, this was
achieved with a manually set flow rate of water as opposed to control
valve metered by measured moisture content.
5. The bioremediation products would need to be dosed in a regular
regime that would provide a continuous replenishment of the bacterial
consortium to the area being remediated thus building the most
effective bacterial population for the oxidation of the hydrocarbon
compounds.
The above
conditions were satisfied using the following method:
Prior to the
delivery of hardware and product, initial soil samples were taken as
a baseline for the bioremediation and to ascertain the C:N:P ratio.
An independent laboratory was used to analyze the soil samples. Two
sampling areas were used determined an average value of the
contaminated soil and a control sample of uncontaminated soil. The
soil samples were taken by extracting a plug of soil which was then
placed in a sample jar, inverted and kept at constant temperature in
a polystyrene container until delivered to the laboratory.
The soil was
then tilled to a depth of 250mm.
The initial
values for the C:N:P ratio were given as 100:4:1 rounding to the
nearest whole number. This value was deemed to be close enough to
the required values of 100:5:1, therefore this ratio was not
corrected with the addition of fertilizers.
An
irrigation system comprising 25mm irrigation pipe was laid over the
area. This consisted of a main pipe trunk line running along the west
wall for 10 metres. This trunk main was fed via a 1kW water pump fed
by a 60 litre drum. The drum was replenished from the water main
using a regulator valve to maintain a constant volume of water in the
drum. Five branch pipes were laid 2 metres apart, running at right
angles from the trunk main eastwards across the contaminated area.
Each 30 metre branch pipe was connected to the trunk via a tee piece
and regulating valve. 360 degree irrigation spinners were fixed at 2
metre intervals along each branch pipe. This layout created an
effective grid system of 2 metre squares fed from each irrigation
spinner. The required flow rate of water was then manually set.
Once the
required flow rate was confirmed by monitoring the soil moisture
content for two days, ½ kg of AquaClean-HYDRO (See appendix for
details) was spread evenly over the soil. This dosage of
Aquaclean-HYDRO was repeated every 2 days from the inoculation date.
In order to
dose the Aquaclean-ACF-32 (See appendix for details), 12 liters of
AquaClean ACF-32 as an inoculation dose was poured into the 60 litre
drum feeding the pump. The main water inflow to the drum created
sufficient turbulence to mix the product with the water. This mixed
product was then pumped into the irrigation system and evenly
distributed via the 360 degree spinners. A quantity of spare spinners
was kept available for replacement for any blocked spinners. These
were replaced as and when required. An AquaClean ACF-32 dosage of 4
litres was then repeated every 2 days from the inoculation date.
This dosing
regime ran for 44 days from 15 May 2010 to 28 July 2010. The total
product utilized was therefore 11kg of AquaClean-HYDRO and 36 liters
of AquaClean ACF-32.
The soil was
then tilled to 250mm once every two weeks.
Results
The table
below gives the results of the laboratory analysis.
|
Date |
Sample |
TPH
mg/kg |
|
%
Reduction |
|
|
|
Series
1 |
Series
2 |
|
|
|
|
|
|
|
|
13th May 2010 |
1 |
17630 |
151 |
|
|
8th June 2010 |
2 |
16012 |
701 |
9.178 |
|
9th July 2010 |
3 |
1684 |
402 |
90.448 |
|
28th July 2010 |
4 |
1681 |
1433 |
90.465 |
|
|
|
|
|
|
Column 1 is
the date the samples were taken.
Column 2 is
the sample number.
Column 3
gives the TPH value for the sample taken in the contaminated area.
Column 4
gives the TPH value for the sample taken in the uncontaminated area.
Column 5 is
the percentage reduction in TPH relative to Contaminated Sample 1.
The TPH
values are shown graphically below.
It can be
seen from Series 1 that the contamination was reduced from a initial
TPH value of 17630 mg/kg to 16012 mg/kg (Sample 2) during the initial
3 weeks after inoculation. This reduction indicates that the
bacterial consortium from the AquaClean ACF-32 had begun to take hold
and establish itself in the soil. The growth of the consortium
reaches a peak in the second month where the bacterial colony has
grown to a level where the colony/nutrient source optimizes the
oxidation of the hydrocarbons in the soil. Sample 3, at 1684 mg/kg,
indicates a drop of over 90 percent and attainment of the goal This
oxidation process continues at this level for a period of 4 weeks
until the nutrient content supplied by the hydrocarbons has been
depleted to the point where the bacterial colony begins to die off in
relation to the depleted nutrient source.
During the
final 3 weeks of the remediation the bacterial colony has once again
reached equilibrium with the nutrient source, however at a much lower
level. This is the expected outcome of the natural bell curve growth
of organisms in the presence of a finite nutrient source.
Series 2
shows a small upward trend in the TPH value reaching approximately
the same level of TPH value given by series 2. This upward trend is
due to the action of the water/product mix creating a osmotic effect
in the soil where some of the hydrocarbon contamination is spread
throughout the treatment area.
It
is shown in the results that the target TPH value of 2000 mg/kg was
reached and exceeded in 10 weeks with the final value being 1681
mg/kg. This is seen to be a
reduction of 90.465%.
Conclusions
Despite the
short time frame given for the bioremediation trial of the
hydrocarbons in the workshop area at Frito-Lay Simba-Isando, the
AquaClean Methodology chosen for the in-situ reduction of hydrocarbon
contamination in the soil has proven the efficacy of method. The
required result of reducing the contamination to an acceptable level
below 2000 mg/kg TPH was reached in 10 weeks. The method proved to be
extremely cost efficient when compared to any other alternative, and
very effective in meeting the remediation goals.
In
short a successful bioremediation was achieved using the method as
proposed by BluePlanet LLC and Ecological Laboratories. AquaClean
ACF-32 and AquaClean-HYDRO has proven their ability to degrade the
DRO and PRO Hydrocarbons.
This report provides an
overview of the contamination issues found and remediated in the
contaminated workshop area of Frito-Lay Simba-Isando. Every effort
has been made to present the data based on the actual findings, and
the conclusions are based on the total experience gained from the
trial. Where research materials and white papers have been used in
the preparation of this report and proposal, they are listed in the
attached bibliography.
Credits
The author
would like to credit the following for the assistance given during
the entire process.
John Morrell
– President of BluePlanet LLC
for treatment plan and application.
Mark Kurpka
– Technical Vice President of Ecological Laboratories
for method design and analysis.
Lesiba
Kgoogo – Frito-Lay Simba
for on-site dosing of the product and the tilling of the soil.
Bibliography
The
following white papers were used in the process and compiling of this
report.
H.I.Atagana – Bioremediation of
creosote-contaminated soil in South Africa by landfarming -
School of Earth Sciences, Mangosuthu Technikon, Jacobs, Durban, South
Africa - October 2003
M.J. Ayotamuno , R.N. Okparanma , E.K.
Nweneka , S.O.T. Ogaji , S.D. Probert - Bioremediation of a sludge
containing hydrocarbons - Agricultural and Environmental
Engineering Department, Rivers State University of Science and
Technology, School of Engineering, Cranfield University - May 2007
Reuben N. Okparanma, Josiah M.
Ayotamuno and Peremelade P. Araka - Bioremediation of hydrocarbon
contaminated-oil field drill-cuttings with bacterial isolates -Department of Agricultural and Environmental Engineering, Rivers
State University of Science and Technology. - May, 2009
Okoh, A. I. and Trejo-Hernandez,
M. R. - Remediation of petroleum hydrocarbon polluted systems:
Exploiting the bioremediation strategies - Department of
Biochemistry and Microbiology, University of Fort Hare. - December,
2006
Krishan Ramluckan - The
Evaluation of Liquid Hydrocarbon Contamination of Soil around
Petrochemical Tank Farms at a Durban Refinery – 2004
|